Considering 1 No. of fixture
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 25 mm dia gate-valve 25 mm dia Gate Valve | 1 | no | 470 | each | 470 | 470 | |
| 2 | Teflon Fitting fixing materials: Teflon tape | 1.05 | pcs | 17 | per pcs | 17 | 17.85 | |
| 3 | Plumber Labour: Plumber | 0.04 | no | 700 | per day | 700 | 28 | |
| 4 | Skilled labour Skilled labour | 0.09 | no | 600 | per day | 600 | 54 | |
| 5 | Ordinary labour Ordinary labour | 0.07 | no | 550 | per day | 550 | 38.5 | |
| Sub-Total | 608.35 | |||||||
| Contractor's Profit | 10% | 0.1 | 60.84 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 21.29 | |||||
| Total | 690.48 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 55.98 | ||||
| Grand Total | 746.46 | |||||||
| Rate per each | 746 | |||||||
| Rate per each | 746 | |||||||