Considering 1 No. of fixture
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 62 mm dia gate-valve 62 mm dia Gate Valve | 1 | no | 2800 | each | 2800 | 2800 | |
| 2 | Teflon Fitting fixing materials: Teflon tape | 2.62 | pcs | 17 | per pcs | 17 | 44.54 | |
| 3 | Plumber Labour: Plumber | 0.09 | no | 700 | per day | 700 | 63 | |
| 4 | Skilled labour Skilled labour | 0.14 | no | 600 | per day | 600 | 84 | |
| 5 | Ordinary labour Ordinary labour | 0.17 | no | 550 | per day | 550 | 93.5 | |
| Sub-Total | 3085.04 | |||||||
| Contractor's Profit | 10% | 0.1 | 308.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 107.98 | |||||
| Total | 3501.52 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 283.91 | ||||
| Grand Total | 3785.43 | |||||||
| Rate per each | 3785 | |||||||
| Rate per each | 3785 | |||||||