Breakup

50 mm dia brass globe valve

Considering 1 No. of fixture

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 50 mm dia globe-valve 50 mm dia Glove Valve 1 no 1500 each 1500 1500
2 Teflon Fitting fixing materials: Teflon tape 2.05 pcs 17 per pcs 17 34.85
3 Plumber Labour: Plumber 0.07 no 700 per day 700 49
4 Skilled labour Skilled labour 0.12 no 600 per day 600 72
5 Ordinary labour Ordinary labour 0.15 no 550 per day 550 82.5
Sub-Total 1738.35
Contractor's Profit 10% 0.1 173.84
Contractor's Overhead Expenses 3.5% 0.035 60.84
Total 1973.03
Add VAT with adjustment factor. 1.08108 7.5% 0.075 159.98
Grand Total 2133.01
Rate per each 2133
Rate per each 2133