Considering 1 No. of fixture
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 75 mm dia globe-valve 75 mm dia Glove Valve | 1 | no | 4280 | each | 4280 | 4280 | |
| 2 | Teflon Fitting fixing materials: Teflon tape | 3.13 | pcs | 17 | per pcs | 17 | 53.21 | |
| 3 | Plumber Labour: Plumber | 0.1 | no | 700 | per day | 700 | 70 | |
| 4 | Skilled labour Skilled labour | 0.175 | no | 600 | per day | 600 | 105 | |
| 5 | Ordinary labour Ordinary labour | 0.2 | no | 550 | per day | 550 | 110 | |
| Sub-Total | 4618.21 | |||||||
| Contractor's Profit | 10% | 0.1 | 461.82 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 161.64 | |||||
| Total | 5241.67 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 425 | ||||
| Grand Total | 5666.67 | |||||||
| Rate per each | 5667 | |||||||
| Rate per each | 5667 | |||||||