100 mm dia brass globe valve

Considering 1 No. of fixture

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 100 mm dia globe-valve 100 mm dia Glove Valve 1 no 6900 each 6900 6900
2 Teflon Fitting fixing materials: Teflon tape 4.19 pcs 17 per pcs 17 71.23
3 Plumber Labour: Plumber 0.115 no 700 per day 700 80.5
4 Skilled labour Skilled labour 0.19 no 600 per day 600 114
5 Ordinary labour Ordinary labour 0.225 no 550 per day 550 123.75
Sub-Total 7289.48
Contractor's Profit 10% 0.1 728.95
Contractor's Overhead Expenses 3.5% 0.035 255.13
Total 8273.56
Add VAT with adjustment factor. 1.08108 7.5% 0.075 670.83
Grand Total 8944.39
Rate per each 8944
Rate per each 8944