Breakup

12 mm brass check valve

Considering 1 No. of fixture

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 12 mm dia check-valve 12 mm dia Check Valve 1 no 280 each 280 280
2 Teflon Fitting fixing materials: Teflon tape 0.53 pcs 17 per pcs 17 9.01
3 Plumber Labour: Plumber 0.025 no 700 per day 700 17.5
4 Skilled labour Skilled labour 0.075 no 600 per day 600 45
5 Ordinary labour Ordinary labour 0.05 no 550 per day 550 27.5
Sub-Total 379.01
Contractor's Profit 10% 0.1 37.9
Contractor's Overhead Expenses 3.5% 0.035 13.27
Total 430.18
Add VAT with adjustment factor. 1.08108 7.5% 0.075 34.88
Grand Total 465.06
Rate per each 465
Rate per each 465