Considering 1 No. of fixture
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 20 mm dia check-valve 20 mm dia Check Valve | 1 | no | 340 | each | 340 | 340 | |
| 2 | Teflon Fitting fixing materials: Teflon tape | 0.8 | pcs | 17 | per pcs | 17 | 13.6 | |
| 3 | Plumber Labour: Plumber | 0.03 | no | 700 | per day | 700 | 21 | |
| 4 | Skilled labour Skilled labour | 0.08 | no | 600 | per day | 600 | 48 | |
| 5 | Ordinary labour Ordinary labour | 0.06 | no | 550 | per day | 550 | 33 | |
| Sub-Total | 455.6 | |||||||
| Contractor's Profit | 10% | 0.1 | 45.56 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 15.95 | |||||
| Total | 517.11 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 41.93 | ||||
| Grand Total | 559.04 | |||||||
| Rate per each | 559 | |||||||
| Rate per each | 559 | |||||||