Breakup

04.32 Added cost for each additional floor above ground floor for patent stone works.

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Add for each addl. floor above ground floor 1 - 550 per day 25.42 25.42
Sub-Total 25.42
Contractor's Profit 10% 0.1 2.54
Contractor's Overhead Expenses 3.5% 0.035 0.89
Total 28.85
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2.34
Grand Total 31.19
Rate per sft 0.31
Rate per sqm 3.34