Breakup

32 mm brass check valve

Considering 1 No. of fixture

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 32 mm dia check-valve 32 mm dia Check Valve 1 no 650 each 650 650
2 Teflon Fitting fixing materials: Teflon tape 1.32 pcs 17 per pcs 17 22.44
3 Plumber Labour: Plumber 0.05 no 700 per day 700 35
4 Skilled labour Skilled labour 0.1 no 600 per day 600 60
5 Ordinary labour Ordinary labour 0.1 no 550 per day 550 55
Sub-Total 822.44
Contractor's Profit 10% 0.1 82.24
Contractor's Overhead Expenses 3.5% 0.035 28.79
Total 933.47
Add VAT with adjustment factor. 1.08108 7.5% 0.075 75.69
Grand Total 1009.16
Rate per each 1009
Rate per each 1009