Breakup

75 mm brass check valve

Considering 1 No. of fixture

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 75 mm dia check-valve 75 mm dia Check Valve 1 no 3190 each 3190 3190
2 Teflon Fitting fixing materials: Teflon tape 3.13 pcs 17 per pcs 17 53.21
3 Plumber Labour: Plumber 0.1 no 700 per day 700 70
4 Skilled labour Skilled labour 0.175 no 600 per day 600 105
5 Ordinary labour Ordinary labour 0.2 no 550 per day 550 110
Sub-Total 3528.21
Contractor's Profit 10% 0.1 352.82
Contractor's Overhead Expenses 3.5% 0.035 123.49
Total 4004.52
Add VAT with adjustment factor. 1.08108 7.5% 0.075 324.69
Grand Total 4329.21
Rate per each 4329
Rate per each 4329