100 mm brass check valve

Considering 1 No. of fixture

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 100 mm dia check-valve 100 mm dia Check Valve 1 no 5400 each 5400 5400
2 Teflon Fitting fixing materials: Teflon tape 4.19 pzs 17 per pcs 17 71.23
3 Plumber Labour: Plumber 0.115 no 700 per day 700 80.5
4 Skilled labour Skilled labour 0.19 no 600 per day 600 114
5 Ordinary labour Ordinary labour 0.225 no 550 per day 550 123.75
Sub-Total 5789.48
Contractor's Profit 10% 0.1 578.95
Contractor's Overhead Expenses 3.5% 0.035 202.63
Total 6571.06
Add VAT with adjustment factor. 1.08108 7.5% 0.075 532.79
Grand Total 7103.85
Rate per each 7104
Rate per each 7104