Considering 1 No. of fixture
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 25 mm dia float-valve 25 mm dia Float Valve | 1 | no | 385 | each | 385 | 385 | |
| 2 | Teflon Fitting fixing materials: Teflon tape | 0.27 | pcs | 17 | per pcs | 17 | 4.59 | |
| 3 | Plumber Labour: Plumber | 0.04 | no | 700 | per day | 700 | 28 | |
| 4 | Skilled labour Skilled labour | 0.09 | no | 600 | per day | 600 | 54 | |
| 5 | Ordinary labour Ordinary labour | 0.07 | no | 550 | per day | 550 | 38.5 | |
| Sub-Total | 510.09 | |||||||
| Contractor's Profit | 10% | 0.1 | 51.01 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 17.85 | |||||
| Total | 578.95 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 46.94 | ||||
| Grand Total | 625.89 | |||||||
| Rate per each | 626 | |||||||
| Rate per each | 626 | |||||||