Considering 1 No. of fixture
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 50 mm plastic Y or T-Y cleanout 50 mm dia plastic Y or T-Y cleanout | 1 | no | 180 | each | 180 | 180 | |
| 2 | Solvent cement Jointing materials : Solvent cement | 10 | ml | 0.85 | per ml | 0.85 | 8.5 | |
| 3 | Plumber Labour: Plumber | 0.025 | no | 700 | per day | 700 | 17.5 | |
| 4 | Skilled labour Skilled labour | 0.05 | no | 600 | per day | 600 | 30 | |
| 5 | Ordinary labour Ordinary labour | 0.095 | no | 550 | per day | 550 | 52.25 | |
| Sub-Total | 288.25 | |||||||
| Contractor's Profit | 10% | 0.1 | 28.83 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 10.09 | |||||
| Total | 327.17 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 26.53 | ||||
| Grand Total | 353.7 | |||||||
| Rate per each | 354 | |||||||
| Rate per each | 354 | |||||||