Breakup

50 mm dia uPVC Y or T - Y Cleanout

Considering 1 No. of fixture

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 50 mm plastic Y or T-Y cleanout 50 mm dia plastic Y or T-Y cleanout 1 no 180 each 180 180
2 Solvent cement Jointing materials : Solvent cement 10 ml 0.85 per ml 0.85 8.5
3 Plumber Labour: Plumber 0.025 no 700 per day 700 17.5
4 Skilled labour Skilled labour 0.05 no 600 per day 600 30
5 Ordinary labour Ordinary labour 0.095 no 550 per day 550 52.25
Sub-Total 288.25
Contractor's Profit 10% 0.1 28.83
Contractor's Overhead Expenses 3.5% 0.035 10.09
Total 327.17
Add VAT with adjustment factor. 1.08108 7.5% 0.075 26.53
Grand Total 353.7
Rate per each 354
Rate per each 354