Considering 1 No. of fixture
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 50 mm plastic "P" or "S" trap 50 mm dia plastic "P" or "S" trap | 1 | no | 390 | each | 390 | 390 | |
| 2 | Solvent cement Jointing materials : Solvent cement | 27 | ml | 0.85 | per ml | 0.85 | 22.95 | |
| 3 | Plumber Labour: Plumber | 0.03 | no | 700 | per day | 700 | 21 | |
| 4 | Skilled labour Skilled labour | 0.07 | no | 600 | per day | 600 | 42 | |
| 5 | Ordinary labour Ordinary labour | 0.162 | no | 550 | per day | 550 | 89.1 | |
| Sub-Total | 565.05 | |||||||
| Contractor's Profit | 10% | 0.1 | 56.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 19.78 | |||||
| Total | 641.33 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 52 | ||||
| Grand Total | 693.33 | |||||||
| Rate per each | 693 | |||||||
| Rate per each | 693 | |||||||