Breakup

50 mm dia uPVC ‘P’ or ‘S’ trap

Considering 1 No. of fixture

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 50 mm plastic "P" or "S" trap 50 mm dia plastic "P" or "S" trap 1 no 390 each 390 390
2 Solvent cement Jointing materials : Solvent cement 27 ml 0.85 per ml 0.85 22.95
3 Plumber Labour: Plumber 0.03 no 700 per day 700 21
4 Skilled labour Skilled labour 0.07 no 600 per day 600 42
5 Ordinary labour Ordinary labour 0.162 no 550 per day 550 89.1
Sub-Total 565.05
Contractor's Profit 10% 0.1 56.5
Contractor's Overhead Expenses 3.5% 0.035 19.78
Total 641.33
Add VAT with adjustment factor. 1.08108 7.5% 0.075 52
Grand Total 693.33
Rate per each 693
Rate per each 693