Considering 1 No. of fixture
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 100 mm "Y" or "T-Y" plastic cleanout 100 mm dia plastic | 1 | no | 350 | each | 350 | 350 | |
| 2 | Solvent cement Jointing Materials : Solvent cement | 27 | ml | 0.85 | per ml | 0.85 | 22.95 | |
| 3 | Plumber Labour: Plumber | 0.045 | no | 700 | per day | 700 | 31.5 | |
| 4 | Skilled labour Skilled labour | 0.09 | no | 600 | per day | 600 | 54 | |
| 5 | Ordinary labour Ordinary labour | 0.161 | no | 550 | per day | 550 | 88.55 | |
| Sub-Total | 547 | |||||||
| Contractor's Profit | 10% | 0.1 | 54.7 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 19.15 | |||||
| Total | 620.85 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 50.34 | ||||
| Grand Total | 671.19 | |||||||
| Rate per each | 671 | |||||||
| Rate per each | 671 | |||||||