Breakup

100 mm dia uPVC Y or T - Y Cleanout

Considering 1 No. of fixture

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 100 mm "Y" or "T-Y" plastic cleanout 100 mm dia plastic 1 no 350 each 350 350
2 Solvent cement Jointing Materials : Solvent cement 27 ml 0.85 per ml 0.85 22.95
3 Plumber Labour: Plumber 0.045 no 700 per day 700 31.5
4 Skilled labour Skilled labour 0.09 no 600 per day 600 54
5 Ordinary labour Ordinary labour 0.161 no 550 per day 550 88.55
Sub-Total 547
Contractor's Profit 10% 0.1 54.7
Contractor's Overhead Expenses 3.5% 0.035 19.15
Total 620.85
Add VAT with adjustment factor. 1.08108 7.5% 0.075 50.34
Grand Total 671.19
Rate per each 671
Rate per each 671
Help