Considering 1 No. of fixture
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 100 mm plastic P or S trap 100 mm dia plastic "P" or "S" trap | 1 | no | 250 | each | 250 | 250 | |
| 2 | Solvent cement Jointing materials : Solvent cement | 10 | ml | 0.85 | per ml | 0.85 | 8.5 | |
| 3 | Plumber Labour: Plumber | 0.025 | no | 700 | per day | 700 | 17.5 | |
| 4 | Skilled labour Skilled labour | 0.05 | no | 600 | per day | 600 | 30 | |
| 5 | Ordinary labour Ordinary labour | 0.095 | no | 550 | per day | 550 | 52.25 | |
| Sub-Total | 358.25 | |||||||
| Contractor's Profit | 10% | 0.1 | 35.83 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 12.54 | |||||
| Total | 406.62 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 32.97 | ||||
| Grand Total | 439.59 | |||||||
| Rate per each | 440 | |||||||
| Rate per each | 440 | |||||||