Consider 01 Valve, Considering 1no. Of fixture
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 50 mm dia water pressure reducing valve (MS) Pressure Reducing Valve price | 1 | no | 9200 | each | 9200 | 9200 | |
| 2 | Teflon Fittings fixing materials: Teflon Tape | 0.8 | pcs | 17 | per pcs | 17 | 13.6 | |
| 3 | Plumber Labour: Plumber | 0.03 | no | 700 | per day | 700 | 21 | |
| 4 | Skilled labour Skilled labour | 0.08 | no | 600 | per day | 600 | 48 | |
| 5 | Ordinary labour Ordinary labour | 0.06 | no | 550 | per day | 550 | 33 | |
| Sub-Total | 9315.6 | |||||||
| Contractor's Profit | 10% | 0.1 | 931.56 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 326.05 | |||||
| Total | 10573.21 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 857.29 | ||||
| Grand Total | 11430.5 | |||||||
| Rate per each | 11431 | |||||||
| Rate per each | 11431 | |||||||