Considering 1 no. of item
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 2000 liter capacity Material cost: (A) | 1 | no | 14600 | each | 14600 | 14600 | |
| 3 | Teflon Accessories: Teflon tape | 4 | pcs | 17 | per pcs | 17 | 68 | |
| 4 | Nipples with jum-nuts Nipple with jam-nuts | 4 | nos | 60 | each | 60 | 240 | |
| 5 | Plumber Labour for lifting, installation & connecting pipes: Plumber | 1 | no | 700 | per day | 700 | 700 | |
| 6 | Skilled labour Skilled labour | 1 | no | 600 | per day | 600 | 600 | |
| 7 | Ordinary labour ordinary labour | 1 | no | 550 | per day | 550 | 550 | |
| 2 | Installation cost: (B) Carrying up to site | LS | 320 | |||||
| Sub-Total | 17078 | |||||||
| Contractor's Profit | 10% | 0.1 | 1707.8 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 597.73 | |||||
| Total | 19383.53 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1571.64 | ||||
| Grand Total | 20955.17 | |||||||
| Rate per each | 20955 | |||||||
| Rate per each | 20955 | |||||||