Breakup

300 liter capacity

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 300 liter capacity Material cost: (A) 1 no 3500 each 3500 3500
3 Teflon Accessories: Teflon tape 4 pcs 17 per pcs 17 68
4 Nipples with jum-nuts Nipple with jam-nuts 1 no 60 each 60 60
5 12 mm or 19 mm dia ball cock for water tank 3/4" dia ball cock 1 no 180 each 180 180
6 Plumber Labour for lifting, installation & connecting pipes: Plumber 0.5 no 700 per day 700 350
7 Skilled labour Skilled labour 0.5 no 600 per day 600 300
2 Installation cost: (B) Carrying up to site LS 160
Sub-Total 4618
Contractor's Profit 10% 0.1 461.8
Contractor's Overhead Expenses 3.5% 0.035 161.63
Total 5241.43
Add VAT with adjustment factor. 1.08108 7.5% 0.075 424.98
Grand Total 5666.41
Rate per each 5666
Rate per each 5666