Considering 1 no. of item
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 450 mm long metal cover connection pipe Material: (A) | 1 | no | 112 | each | 112 | 112 | |
| 2 | Plumber Installation cost: (B) Labour: Plumber | 0.05 | no | 700 | per day | 700 | 35 | |
| 3 | Skilled labour Skilled labour | 0.01 | no | 600 | per day | 600 | 6 | |
| Sub-Total | 153 | |||||||
| Contractor's Profit | 10% | 0.1 | 15.3 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 5.36 | |||||
| Total | 173.66 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 14.08 | ||||
| Grand Total | 187.74 | |||||||
| Rate per each | 188 | |||||||
| Rate per each | 188 | |||||||