Considering 1 no. of item
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Water purification capacity: 20 L/hr, minimum storage 8 litre, 6 stage purification; RO+UV+MF Material: (A) | 1 | no | 23000 | each | 23000 | 23000 | |
| 2 | Water purification capacity: 20 L/hr, minimum storage 8 litre, 6 stage purification; RO+UV+MF Installation cost: (B) Installation charge excluding cost of pipe line (2 % of product cost) | 1 | no | 23000 | each | 460 | 460 | |
| 3 | Carriage, incidental, sundries etc. | LS | 500 | |||||
| Sub-Total | 23960 | |||||||
| Contractor's Profit | 10% | 0.1 | 2396 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 838.6 | |||||
| Total | 27194.6 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 2204.97 | ||||
| Grand Total | 29399.57 | |||||||
| Rate per each | 29400 | |||||||
| Rate per each | 29400 | |||||||