Breakup

Automatic Hand drier Local (Standard quality)

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Automatic Hand drier Local (Standard quality) Material: (A) 1 no 4500 each 4500 4500
2 Skilled labour Installation cost: (B) Labour: Skilled labour 0.3 no 600 per day 600 180
3 Others (Screw, royal bolt, washer etc.) LS 50
Sub-Total 4730
Contractor's Profit 10% 0.1 473
Contractor's Overhead Expenses 3.5% 0.035 165.55
Total 5368.55
Add VAT with adjustment factor. 1.08108 7.5% 0.075 435.29
Grand Total 5803.84
Rate per each 5804
Rate per each 5804