Breakup

Automatic Hand drier Local (Suprior quality)

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Automatic Hand drier Local (Superior quality) Material: (A) 1 no 7000 each 7000 7000
2 Skilled labour Installation cost: (B) Labour: Skilled labour 0.3 no 600 per day 600 180
3 Others (Screw, royal bolt, washer etc.) LS 50
Sub-Total 7230
Contractor's Profit 10% 0.1 723
Contractor's Overhead Expenses 3.5% 0.035 253.05
Total 8206.05
Add VAT with adjustment factor. 1.08108 7.5% 0.075 665.35
Grand Total 8871.4
Rate per each 8871
Rate per each 8871