Breakup

Automatic Hand drier (Special quality)

Considering 1 no. of item

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Automatic Hand drier (Special quality) Material: (A) 1 no 11200 each 11200 11200
2 Skilled labour Installation cost: (B) Labour: Skilled labour 0.3 no 600 per day 600 180
3 Others (Screw, royal bolt, washer etc.) LS 50
Sub-Total 11430
Contractor's Profit 10% 0.1 1143
Contractor's Overhead Expenses 3.5% 0.035 400.05
Total 12973.05
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1051.87
Grand Total 14024.92
Rate per each 14025
Rate per each 14025