Considering 6'-0" long hanger
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | M.S. angle, T and Z-section, Channel etc. Total rft of Angle: 1x 6'-0"= 6.00 ft (a)Cost of 38mm x 38mm x 6mm M.S. angle for vertical: @ 2.34 Ibs per ft (1x6'-0"=6ft + Add wastage 5%=0.3ft)=6.3ft=14.74Ibs | 14.74 | lbs | 70000 | per M. ton | 31.75 | 468 | |
| 2 | 1/2" x 2.5" nut-bolt Cost of 12mm dia Nut-bolt with rowel bolt. | 6 | each | 32 | each | 32 | 192 | |
| 3 | Ordinary labour Cutting charge of M.S. angle as per required measurement in/c cost of T & P. | 1 | no | 550 | per day | 10 | 10 | |
| 4 | Mason / Mosaic mistry Labour charge for fixing up the M.S. angle in the nosing of steps to keep the angles in level and parallel with each of the ceiling : Mason | 0.5 | no | 700 | per day | 700 | 350 | |
| 5 | Ordinary labour Ordinary labour | 0.5 | no | 550 | per day | 550 | 275 | |
| Sub-Total | 1295 | |||||||
| Contractor's Profit | 10% | 0.1 | 129.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 45.33 | |||||
| Total | 1469.83 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 119.18 | ||||
| Grand Total | 1589.01 | |||||||
| Rate per ft | 264.83 | |||||||
| Rate per meter | 868.91 | |||||||