Considering 3 meter long grove
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement mortar (1:4) : Cement | 0.024 | bag | 410 | per bag | 410 | 9.84 | |
| 2 | Sand (F.M. 1.2) Sand (F.M. 1.2) | 0.12 | cft | 1900 | per % cft | 19 | 2.2800000000000002 | |
| 3 | Plumber Labour: Plumber | 0.06 | no | 700 | per day | 700 | 42 | |
| 4 | Skilled labour Skilled labour | 0.12 | no | 600 | per day | 600 | 72 | |
| 5 | Ordinary labour Ordinary labour | 0.248 | no | 550 | per day | 550 | 136.4 | |
| Sub-Total | 262.52 | |||||||
| Contractor's Profit | 10% | 0.1 | 26.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 9.19 | |||||
| Total | 297.96 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 24.16 | ||||
| Grand Total | 322.12 | |||||||
| Rate per each | 322 | |||||||
| Rate per each | 322 | |||||||