Groove size 40 mm x 40 mm (For laying 12 mm to 20 mm dia pipes)

Considering 3 meter long grove

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement mortar (1:4) : Cement 0.024 bag 410 per bag 410 9.84
2 Sand (F.M. 1.2) Sand (F.M. 1.2) 0.12 cft 1900 per % cft 19 2.2800000000000002
3 Plumber Labour: Plumber 0.06 no 700 per day 700 42
4 Skilled labour Skilled labour 0.12 no 600 per day 600 72
5 Ordinary labour Ordinary labour 0.248 no 550 per day 550 136.4
Sub-Total 262.52
Contractor's Profit 10% 0.1 26.25
Contractor's Overhead Expenses 3.5% 0.035 9.19
Total 297.96
Add VAT with adjustment factor. 1.08108 7.5% 0.075 24.16
Grand Total 322.12
Rate per each 322
Rate per each 322