Breakup

Groove size 75 mm x 75 mm (For 25 mm to 40 mm dia pipes)

Considering 3 meter long grove

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement mortar (1:4) : Cement 0.1 bag 410 per bag 410 41
2 Sand (F.M. 1.2) Sand (F.M. 1.2) 0.5 cft 1900 per % cft 19 9.5
3 Plumber Labour: Plumber 0.09 no 700 per day 700 63
4 Skilled labour Skilled labour 0.156 no 600 per day 600 93.6
5 Ordinary labour Ordinary labour 0.4 no 550 per day 550 220
Sub-Total 427.1
Contractor's Profit 10% 0.1 42.71
Contractor's Overhead Expenses 3.5% 0.035 14.95
Total 484.76
Add VAT with adjustment factor. 1.08108 7.5% 0.075 39.3
Grand Total 524.06
Rate per each 524
Rate per each 524