Breakup

Punching or cutting hole of any diameter in RCC floor for sanitary works.

Break-up for 6" dia 1 hole

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 0.1 no 600 per day 600 60
2 Ordinary labour Ordinary labour 0.1 no 550 per day 550 55
3 Ordinary labour Tools and plant, sundries etc. 1 LS 550 per day 25 25
4 Ordinary labour Mending good the damages 1 LS 550 per day 25 25
Sub-Total 165
Contractor's Profit 10% 0.1 16.5
Contractor's Overhead Expenses 3.5% 0.035 5.78
Total 187.28
Add VAT with adjustment factor. 1.08108 7.5% 0.075 15.18
Grand Total 202.46
Rate per each 202
Rate per each 202
Help