Considering 1 no. of item
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Water sealed heavy type 24" / 600 mm dia C.I. M.H. cover having locking arrangement Material: (A) | 1 | no | 1400 | each | 1400 | 1400 | |
| 2 | Ordinary labour Installation cost: (B) Labour: for placing pit cover : Ordinary labour | 0.15 | no | 550 | per day | 550 | 82.5 | |
| Sub-Total | 1482.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 148.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 51.89 | |||||
| Total | 1682.64 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 136.43 | ||||
| Grand Total | 1819.07 | |||||||
| Rate per each | 1819 | |||||||
| Rate per each | 1819 | |||||||