for single 150mm dia size RCC pipes Considering 1 No. pit
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Earthwork in excavation Earth-work: 1 x 3-4" x 3'-4" x 2'-3"= 24.95 cft | 24.95 | cft | 4979.17 | % 0 cft | 4.98 | 124.25 | |
| 2 | One layer brick-flat soling Brick-flat soling: 1 x 3'-2" x 3'-2"= 10.04 sft | 10.04 | sft | 36.19 | % sft | 0.36 | 3.61 | |
| 3 | Plain concrete (1:3:6) with brick chips C.C. (1:3:6) on soling: 1 x 3'-2" x 3'-2" x 0'-3"= 2.51 cft | 2.51 | cft | 17561.67 | % cft | 175.62 | 440.81 | |
| 4 | Plain concrete (1:3:6) with brick chips C.C. (1:3:6) for invert: 1 x 1'-6" x 1'-6" x 0'-2"= 0.38 cft | 0.38 | cft | 17561.67 | % cft | 175.62 | 66.74 | |
| 5 | Brick work (1:6) in foundation Brick-work (1:6): 2 x (3'-2" + 1'-6") x 1'-9" x 0'-10"= 13.57 cft | 13.57 | cft | 17397.25 | % cft | 173.97 | 2360.77 | |
| 6 | 1/2 " thick plaster (1:4) with N.C.F. 12 mm plaster with n.c.f.: 4 x (1'-6" x 1'- 6") + 1' - 6" x 1'- 6"= 12.75 sft | 12.75 | cft | 28.39 | sft | 0.28 | 3.57 | |
| 7 | Plumber Plumber | 0.125 | no | 700 | per day | 700 | 87.5 | |
| 8 | Skilled labour Skilled labour | 0.125 | no | 600 | per day | 600 | 75 | |
| 9 | Ordinary labour Ordinary labour | 0.25 | no | 550 | per day | 550 | 137.5 | |
| Sub-Total | 3299.75 | |||||||
| Contractor's Profit | 10% | 0.1 | 329.98 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 115.49 | |||||
| Total | 3745.22 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 303.67 | ||||
| Grand Total | 4048.89 | |||||||
| Rate per no | 4049 | |||||||
| Rate per each | 4049 | |||||||