for single 300mm dia size RCC or 375 mm plastic/PVC pipes, 1 No. pit
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Earthwork in excavation Earth-work: 1 x 3'-11" x 3'-11" x 3'-3"= 49.94 cft | 49.94 | cft | 4979.17 | % 0 cft | 4.98 | 248.7 | |
| 2 | One layer brick-flat soling Brick-flat soling: 1 x 3'-8" x 3'-8"= 13.47 sft | 13.47 | sft | 36.19 | % sft | 0.36 | 4.85 | |
| 3 | Plain concrete (1:3:6) with brick chips C.C. (1:3:6) on soling: 1 x 3'-8" x 3'-8" x 0'-3"= 3.37 cft | 3.37 | cft | 17561.67 | % cft | 175.62 | 591.84 | |
| 4 | Plain concrete (1:3:6) with brick chips C.C. (1:3:6) for invert: 1 x 2'-0" x 2'-0" x 0'-2"= 0.67 cft | 0.67 | cft | 17561.67 | % cft | 175.62 | 117.67 | |
| 5 | Brick work (1:6) in foundation Brick-work (1:6): 2 x (3'-8" + 2'-0") x 2'-9" x 0'-10"= 31.19 cft | 31.19 | cft | 17397.25 | % cft | 173.97 | 5426.12 | |
| 6 | 1/2 " thick plaster (1:4) with N.C.F. 12 mm plaster with n.c.f.: 4 x (2'-0" x 2'-9") + 2'-6" x 2'-6"= 28.25 sft | 28.25 | sft | 28.39 | sft | 0.28 | 7.91 | |
| 7 | Plumber Plumber | 0.14 | no | 700 | per day | 700 | 98 | |
| 8 | Skilled labour Skilled labour | 0.23 | no | 600 | per day | 600 | 138 | |
| 9 | Ordinary labour Ordinary labour | 0.27 | no | 550 | per day | 550 | 148.5 | |
| Sub-Total | 6781.59 | |||||||
| Contractor's Profit | 10% | 0.1 | 678.16 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 237.36 | |||||
| Total | 7697.11 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 624.09 | ||||
| Grand Total | 8321.2 | |||||||
| Rate per no | 8321 | |||||||
| Rate per each | 8321 | |||||||