Considering 1 No. pit cover
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Concrete for slab (1:2:4) R.C.C. (1:2:4) for slab: 1 x 3'-8" x 3'-8" x 0'-3"= 3.37 cft | 3.37 | cft | 20355.5 | % cft | 203.56 | 686 | |
| 2 | Grade 300(300Mpa / 300N/mm2 ≈ 43500psi/40 Grade): BDS- 6935-2006 - B300 and Ratio fy to fu =>1.25 1% re-inforcement in/c fabrication | 16.51 | lbs | 65000 | per M. ton | 29.48 | 486.71 | |
| 3 | 1/2 " thick plaster (1:4) with N.C.F. 12 mm plaster with n.c.f.: 4 x 3'-8" x 0'-3" + 3'-8" x 3'-8"= 17.14 sft | 17.14 | sft | 28.39 | sft | 0.28 | 4.8 | |
| 4 | Ordinary labour Extra labour for placing pit cover Ordinary labour | 0.1 | no | 550 | per day | 550 | 55 | |
| Sub-Total | 1232.51 | |||||||
| Contractor's Profit | 10% | 0.1 | 123.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 43.14 | |||||
| Total | 1398.9 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 113.42 | ||||
| Grand Total | 1512.32 | |||||||
| Rate per no | 1512 | |||||||
| Rate per each | 1512 | |||||||