Breakup

01.6 Providing layout and carry over PWD bench-mark (BM) at site from nearby BM pillar, property lines, existing ground level (EGL), formation ground level (FGL), highest flood levels (HFL), plinth levels (PL), mean sea level (MSL), setting and marking all pillars, marker, pegs etc. showing and maintaining reduced levels (RL’s) including locating, establishing, protecting all public utilities within the premise of work and finally all to be presented in black and white.

Considering 5000 sft ground area

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Surveyor (10yrs Exp / diploma Engineer trained in survey ) Surveyor 0.5 no 1400 per day 1400 700
2 Helper to surveyor Helper to surveyor 0.5 no 800 per day 800 400
3 Hire charge of survey instrument (Level / Theodolite etc.) Hire charge of Level/Theodolite 1 set 1000 per day 1000 1000
4 Ordinary labour Ordinary labour 2 nos 550 per day 550 1100
5 Ordinary labour Cost for construct and protect bench-mark, test pit etc. 1 LS 550 per day 7906.25 7906.25
6 Ordinary labour Tools and plant, spike, nails, chalk-powder etc. 1 LS 550 per day 1375 1375
Sub-Total 12481.25
Contractor's Profit 10% 0.1 1248.13
Contractor's Overhead Expenses 3.5% 0.035 436.84
Total 14166.22
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1148.61
Grand Total 15314.83
Rate per sft 3.06
Rate per sqm 32.94