Considering 5000 sft ground area
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Surveyor (10yrs Exp / diploma Engineer trained in survey ) Surveyor | 0.5 | no | 1400 | per day | 1400 | 700 | |
| 2 | Helper to surveyor Helper to surveyor | 0.5 | no | 800 | per day | 800 | 400 | |
| 3 | Hire charge of survey instrument (Level / Theodolite etc.) Hire charge of Level/Theodolite | 1 | set | 1000 | per day | 1000 | 1000 | |
| 4 | Ordinary labour Ordinary labour | 2 | nos | 550 | per day | 550 | 1100 | |
| 5 | Ordinary labour Cost for construct and protect bench-mark, test pit etc. | 1 | LS | 550 | per day | 7906.25 | 7906.25 | |
| 6 | Ordinary labour Tools and plant, spike, nails, chalk-powder etc. | 1 | LS | 550 | per day | 1375 | 1375 | |
| Sub-Total | 12481.25 | |||||||
| Contractor's Profit | 10% | 0.1 | 1248.13 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 436.84 | |||||
| Total | 14166.22 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1148.61 | ||||
| Grand Total | 15314.83 | |||||||
| Rate per sft | 3.06 | |||||||
| Rate per sqm | 32.94 | |||||||