Breakup

26.72.2 1025 mm x 1025 mm x 75 mm R.C.C. pit cover with 450 mm dia C.I. manhole cover.

Considering 1 No. pit cover with man-hole cover

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Concrete for slab (1:2:4) R.C.C. (1:2:4) for slab: 1 x (3'-5" x 3'-5"- 0.785 x 1'-6" x 1'-6") x 0'-3" = 2.48 cft 2.48 cft 20355.5 % cft 203.56 504.83
2 Grade 300(300Mpa / 300N/mm2 ≈ 43500psi/40 Grade): BDS- 6935-2006 - B300 and Ratio fy to fu =>1.25 1% re-inforcement in/c fabrication 12.15 lbs 65000 per M. ton 29.48 358.18
3 1/2 " thick plaster (1:4) with N.C.F. 12 mm plaster with n.c.f.: 4 x (3'-5" x 0'-3" + 3'-5" x 3'-5" - 0.785 x 1'-6" x 1'-6") = 13.35 sft 13.35 sft 28.39 sft 0.28 3.74
4 Water sealed heavy type 18" / 450 mm dia C.I. M.H. cover having locking arrangement 18" dia water sealed heavy type C.I. man-hole cover with locking arrangement in/c making holes. 1 no 910 each 910 910
5 Ordinary labour Extra labour for placing pit cover Ordinary labour 0.1 no 550 per day 550 55
Sub-Total 1831.75
Contractor's Profit 10% 0.1 183.18
Contractor's Overhead Expenses 3.5% 0.035 64.11
Total 2079.04
Add VAT with adjustment factor. 1.08108 7.5% 0.075 168.57
Grand Total 2247.61
Rate per no 2248
Rate per each 2248