Breakup

26.74.1 For 200 users

Considering 1 No. septic tank

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Earthwork in excavation Earth-work: 1 x 25-2" x 10'-8" x 6'-9" = 1812.81 cft 1812.81 cft 4979.17 % 0 cft 4.98 9027.79
2 One layer brick-flat soling Brick-flat soling: 1 x 24'-8" x 10'-2" = 250.89 sft 250.89 sft 36.19 % sft 0.36 90.32
3 Concrete for slab (1:2:4) 6" R. C.C. (1:2:4) on soling: 1 x 24'-8" x 10'-2" x 0'-6" = 125.45 cft 125.45 cft 20355.5 % cft 203.56 25536.6
4 Concrete for slab (1:2:4) 5" thick R.C.C.(1:2"4) lining 2 x (23'-0" + 6'-0") x 6'-8" x 5" = 162.48 cft 162.48 cft 20355.5 % cft 203.56 33074.43
5 Concrete for slab (1:2:4) Tie beam (1:2:4) 1 x 9" x 9" x 6'-0" = 3.38 cft 3.38 cft 20355.5 % cft 203.56 688.03
6 Concrete for slab (1:2:4) R.C.C. in roof slab 1 x 24' - 8" x 8' - 6" x 4" = 69.20 cft 69.2 cft 20355.5 % cft 203.56 14086.35
7 Brick work (1:6) in foundation Brick-work (1:6): 2 x 24'-8" x 2'-0" x 10" = 81.90 cft 2 x 24'-8" x 1'-0" x 5" = 20.72 cft 1 x (24'-8" + 6'-10") x 6'-8" x 10" 348.8 cft 1 x (7'-8" x 1'- 6" x 0'-10" ) 9.6 cft Total = 461.02 cft 461.02 cft 17397.25 % cft 173.97 80203.65
8 5" / 125 mm brickwork (1:6) 5" thick brick-work (1:6) 6'-0" x 4'-5" = 26.52 sft 6'-0" x 5'-6" = 33.00 sft = 59.52 sft 59.52 sft 8794.75 % sft 87.95 5234.78
9 1/2 " thick plaster (1:4) with N.C.F. 12 mm plaster with n.c.f.: Floor: 1 x 22' - 2" x 6' - 0" = 133.02 sft Walls:2x(22'-2"+ 5'-11") x 6'-7.5" = 371.78 sft Tie: 1 x 6' - 0" x 2' - 7" = 15.48 sft Outside: 2x(24'-8"+ 8'-6")x1'-6" = 99.51 sft = 619.79 sft 619.79 sft 28.39 sft 0.28 173.54
10 RCC tees RCC Tees 2 nos 450 each 450 900
11 Grade 300(300Mpa / 300N/mm2 ≈ 43500psi/40 Grade): BDS- 6935-2006 - B300 and Ratio fy to fu =>1.25 re-inforcement & fabrication 1212 lbs 65000 per M. ton 29.48 35729.76
12 Water sealed heavy type 18" / 450 mm dia C.I. M.H. cover having locking arrangement 18" dia water sealed heavy type C.I. man-hole cover with locking arrangement in/c making holes. 3 nos 910 each 910 2730
13 Side filling, dressing, inside cleaning etc. LS 1600
Sub-Total 209075.25
Contractor's Profit 10% 0.1 20907.53
Contractor's Overhead Expenses 3.5% 0.035 7317.63
Total 237300.41
Add VAT with adjustment factor. 1.08108 7.5% 0.075 19240.55
Grand Total 256540.96
Rate per no 256541
Rate per each 256541
Help