Breakup

26.74.2 For 100 users

Considering 1 No. septic tank

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Earthwork in excavation Earth-work: 1 x 20-5" x 8'-10" x 6'-8" = 1202.66 cft 1202.66 cft 4979.17 % 0 cft 4.98 5989.25
2 One layer brick-flat soling Brick-flat soling 1 x 19'-11" x 8'-4" = 165.93 sft 165.93 sft 36.19 % sft 0.36 59.73
3 Concrete for slab (1:2:4) 6" R. C.C. (1:2:4) on soling: 1 x 19'-11" x 8'-4" x 0'-6" = 82.97 cft 82.97 cft 20355.5 % cft 203.56 16889.37
4 Concrete for slab (1:2:4) 5" thick R.C.C.(1:2"4) lining 2 x (18'-3" + 4'-2") x 6'-8" x 5" = 125.61 cft 125.61 cft 20355.5 % cft 203.56 25569.17
5 Concrete for slab (1:2:4) Tie beam (1:2:4) 1 x 9" x 9" x 4'-2" = 2.35 cft 2.35 cft 20355.5 % cft 203.56 478.37
6 Concrete for slab (1:2:4) R.C.C. in roof slab 1 x 19' - 11" x 6' - 8" x 4" = 43.85 cft 43.85 cft 20355.5 % cft 203.56 8926.11
7 Brick work (1:6) in foundation Brick-work (1:6): 2 x 19'-11" x 2'-0" x 10" = 66.13 cft 2 x 19'-11" x 1'-0" x 5" = 16.73 cft 2 x (19'-11" + 5'-0") x 6'-8" = 332.43 cft 1 x (5'-10" x 1'- 6" x 0'-10" ) 7.26 cft Total = 422.55 cft 422.55 cft 17397.25 % cft 173.97 73511.02
8 5" / 125 mm brickwork (1:6) 5" thick brick-work (1:6) 4'-2" x 4'-5" = 18.43 sft 4'-2" x 5'-2" = 21.56 sft = 39.99 sft 39.99 sft 8794.75 % sft 87.95 3517.12
9 1/2 " thick plaster (1:4) with N.C.F. 12 mm plaster with n.c.f.: Floor: 1 x 17' - 5" x 4' - 2" = 72.64 sft Walls: 2 x (17' - 5" + 4'-1") x 6' - 7.5" = 284.66 sft Tie: 1 x 4' -0" x 2' - 7" = 8.68 sft Outside: 2 x (19'-11" + 6'-8") x 1'-6" = 79.74 sft = 445.72 sft 445.72 sft 28.39 sft 0.28 124.8
10 RCC tees RCC Tees 2 nos 450 each 450 900
11 Grade 300(300Mpa / 300N/mm2 ≈ 43500psi/40 Grade): BDS- 6935-2006 - B300 and Ratio fy to fu =>1.25 re-inforcement & fabrication 883 lbs 65000 per M. ton 29.48 26030.84
12 Water sealed heavy type 18" / 450 mm dia C.I. M.H. cover having locking arrangement 18" dia water sealed heavy type C.I. man-hole cover with locking arrangement in/c making holes. 3 nos 910 each 910 2730
13 Side filling, dressing, inside cleaning etc. LS 1280
Sub-Total 166005.78
Contractor's Profit 10% 0.1 16600.58
Contractor's Overhead Expenses 3.5% 0.035 5810.2
Total 188416.56
Add VAT with adjustment factor. 1.08108 7.5% 0.075 15277
Grand Total 203693.56
Rate per no 203694
Rate per each 203694
Help