Breakup

26.74.3 For 50 users

Considering 1 No. septic tank

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Earthwork in excavation Earth-work: 1 x 14'-0" x 8'-10" x 5'-5" = 670.02 cft 670.02 cft 4979.17 % 0 cft 4.98 3336.7
2 One layer brick-flat soling Brick-flat soling 1 x 13'-6" x 8'-4" = 112.46 sft 112.46 sft 36.19 % sft 0.36 40.49
3 Concrete for slab (1:2:4) 6" R. C.C. (1:2:4) on soling: 1 x 13'-6" x 8'-4" x 0'-6" = 56.23 cft 56.23 cft 20355.5 % cft 203.56 11446.18
4 Concrete for slab (1:2:4) 5" thick R.C.C.(1:2"4) lining 2 (11'-10" + 4' - 2") x 6' - 4" x 5" = 85.08 cft 85.08 cft 20355.5 % cft 203.56 17318.88
5 Concrete for slab (1:2:4) Tie beam (1:2:4) 1 x 9" x 9" x 4'-2" = 2.35 cft 2.35 cft 20355.5 % cft 203.56 478.37
6 Concrete for slab (1:2:4) R.C.C. in roof slab 1 x 13' - 6" x 6' - 8" x 4" = 29.71 cft 29.71 cft 20355.5 % cft 203.56 6047.77
7 Brick work (1:6) in foundation Brick-work (1:6): 2 x 13'-6" x 2'-0" x 10" = 44.82 cft 2 x 13'-6" x 1'-0" x 5" = 11.34 cft 2 x (13'-6" + 5'-0") x 5'-4" x 10" = 163.6843 cft 1x 5'-10" x 1'-6" x 10" = 7.26 cft Total = 227.1043 cft 227.1043 cft 17397.25 % cft 173.97 39509.34
8 5" / 125 mm brickwork (1:6) 5" thick brick-work (1:6) 4'-2" x 4'-1" = 17.01 sft 4'-2" x 4'-10" = 20.14 sft = 37.15 sft 37.15 sft 8794.75 % sft 87.95 3267.34
9 1/2 " thick plaster (1:4) with N.C.F. 12 mm plaster with n.c.f.: Floor: 1 x 11' - 0" x 4' - 2" = 45.87 sft Walls: 2 x (11' - 0" + 4'-1") x 6' - 3.5" = 189.71 sft Tie: 1 x 2' - 7" x 4' - 2" = 10.76 sft Outside: 2 x (13'-6" + 6'-8") x 1'-6" = 60.51 sft = 306.85 sft 306.85 sft 28.39 sft 0.28 85.92
10 RCC tees RCC Tees 2 nos 450 each 450 900
11 Grade 300(300Mpa / 300N/mm2 ≈ 43500psi/40 Grade): BDS- 6935-2006 - B300 and Ratio fy to fu =>1.25 re-inforcement & fabrication 587 lbs 65000 per M. ton 29.48 17304.76
12 Water sealed heavy type 18" / 450 mm dia C.I. M.H. cover having locking arrangement 18" dia water sealed heavy type C.I. man-hole cover with locking arrangement in/c making holes. 3 nos 910 each 910 2730
13 Side filling, dressing, inside cleaning etc. LS 1120
Sub-Total 103585.75
Contractor's Profit 10% 0.1 10358.58
Contractor's Overhead Expenses 3.5% 0.035 3625.5
Total 117569.83
Add VAT with adjustment factor. 1.08108 7.5% 0.075 9532.68
Grand Total 127102.51
Rate per no 127103
Rate per each 127103
Help