Breakup

26.74.4 For 30 users

Considering 1 No. septic tank

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Earthwork in excavation Earth-work: 1 x 12'-0" x 7'-2" x 6'-1.5" = 526.56 cft 526.56 cft 4979.17 % 0 cft 4.98 2622.27
2 One layer brick-flat soling Brick-flat soling 1 x 11'-6" x 6'-8" = 76.71 sft 76.71 sft 36.19 % sft 0.36 27.62
3 Concrete for slab (1:2:4) 6" R. C.C. (1:2:4) on soling: 1 x 11'-6" x 6'-8" x 0'-6" = 37.38 cft 37.38 cft 20355.5 % cft 203.56 7609.07
4 Concrete for slab (1:2:4) 5" thick R.C.C.(1:2"4) lining 2 (9'-10" + 2' - 6") x 5' - 8" x 5" = 58.73 cft 58.73 cft 20355.5 % cft 203.56 11955.08
5 Concrete for slab (1:2:4) Tie beam (1:2:4) 1 x 9" x 9" x 2'-6" = 1.41 cft 1.41 cft 20355.5 % cft 203.56 287.02
6 Concrete for slab (1:2:4) R.C.C. in roof slab 1 x 11' - 6" x 5' - 0" x 4" = 18.98 cft 18.98 cft 20355.5 % cft 203.56 3863.57
7 Brick work (1:6) in foundation Brick-work (1:6): 2 x 11' - 6" x 2'-0" x 10" = 38.18 cft 2 x 11' - 6" x 1'-0" x 5" = 9.66 cft 2 x (11' - 6" + 3' - 2") x 5' - 8" x 10" = 138.08 cft 1x 4'-2" x 1'-6" x 10" = 5.19 cft Total = 191.11 cft 191.11 cft 17397.25 % cft 173.97 33247.41
8 5" / 125 mm brickwork (1:6) 5" thick brick-work (1:6) 1 x 2' - 6" x 3'-5" = 8.55 sft 8.55 sft 8794.75 % sft 87.95 751.97
9 1/2 " thick plaster (1:4) with N.C.F. 12 mm plaster with n.c.f.: Floor: 1 x 9' - 0" x 2' - 6" = 22.50 sft Walls: 2 x (9' - 0" + 2'-1") x 5' - 8" = 125.65 sft Tie: 1 x 2' - 7" x 2' - 5" = 6.24 sft Outside: 2 x (11'-6" + 5'-0") x 1'-6" = 49.50 sft = 203.89 sft 203.89 sft 28.39 sft 0.28 57.09
10 RCC tees RCC Tees 2 nos 450 each 450 900
11 Grade 300(300Mpa / 300N/mm2 ≈ 43500psi/40 Grade): BDS- 6935-2006 - B300 and Ratio fy to fu =>1.25 re-inforcement & fabrication 432 lbs 65000 per M. ton 29.48 12735.36
12 Water sealed heavy type 18" / 450 mm dia C.I. M.H. cover having locking arrangement 18" dia water sealed heavy type C.I. man-hole cover with locking arrangement in/c making holes. 2 nos 910 each 910 1820
13 Side filling, dressing, inside cleaning etc. LS 960
Sub-Total 76836.46
Contractor's Profit 10% 0.1 7683.65
Contractor's Overhead Expenses 3.5% 0.035 2689.28
Total 87209.39
Add VAT with adjustment factor. 1.08108 7.5% 0.075 7071.02
Grand Total 94280.41
Rate per no 94280
Rate per each 94280
Help