Breakup

26.74.5 For 20 users

Considering 1 No. septic tank

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Earthwork in excavation Earth-work: 1 x 11'-0" x 7'-2" x 6'-1.5" = 482.68 cft 482.68 cft 4979.17 % 0 cft 4.98 2403.75
2 One layer brick-flat soling Brick-flat soling 1 x 10'-6" x 6'-6" = 68.25 sft 68.25 sft 36.19 % sft 0.36 24.57
3 Concrete for slab (1:2:4) 6" R. C.C. (1:2:4) on soling: 1 x 10'-6" x 6'-6" x 0'-6" = 34.13 cft 34.13 cft 20355.5 % cft 203.56 6947.5
4 Concrete for slab (1:2:4) 5" thick R.C.C.(1:2:4) lining 2 x (8'-10" + 2'-6") x 5' - 8" x 5" = 53.96 cft 53.96 cft 20355.5 % cft 203.56 10984.1
5 Concrete for slab (1:2:4) Tie beam (1:2:4) 1 x 9" x 9" x 2'-6" = 1.41 cft 1.41 cft 20355.5 % cft 203.56 287.02
6 Concrete for slab (1:2:4) R.C.C. in roof slab 1 x 10' - 6" x 6' - 8" x 4" = 23.11 cft 23.11 cft 20355.5 % cft 203.56 4704.27
7 Brick work (1:6) in foundation Brick-work (1:6): 2 x 10'-6" x 2'-0" x 10" = 34.86 cft 2 x 10'-6" x 1'-0" x 5" = 8.82 cft 2 x (10'-6" + 3' - 2") x 5'-8" x 10" = 128.66 cft 1x 4'-2" x 1'-6" x 10" = 5.19 cft Total = 177.53 cft 177.53 cft 17397.25 % cft 173.97 30884.89
8 5" / 125 mm brickwork (1:6) 5" thick brick-work (1:6) 2'-6" x 3'-5" = 8.55 sft 8.55 sft 8794.75 % sft 87.95 751.97
9 1/2 " thick plaster (1:4) with N.C.F. 12 mm plaster with n.c.f.: Floor: 1 x 8' - 0" x 2' - 6" = 20.00 sft Walls: 2 x (8' - 0" + 2'-5") x 5' - 8" = 118.16 sft Tie: 1 x 2' - 7" x 2' - 5" = 6.24 sft Outside: 2 x (10'-6" + 5'-0") x 1'-6" = 46.50 sft = 190.90 sft 190.9 sft 28.39 sft 0.28 53.45
10 RCC tees RCC Tees 2 nos 450 each 450 900
11 Grade 300(300Mpa / 300N/mm2 ≈ 43500psi/40 Grade): BDS- 6935-2006 - B300 and Ratio fy to fu =>1.25 re-inforcement & fabrication 389 lbs 65000 per M. ton 29.48 11467.72
12 Water sealed heavy type 18" / 450 mm dia C.I. M.H. cover having locking arrangement 18" dia water sealed heavy type C.I. man-hole cover with locking arrangement in/c making holes. 2 nos 910 each 910 1820
13 Side filling, dressing, inside cleaning etc. LS 800
Sub-Total 72029.24
Contractor's Profit 10% 0.1 7202.92
Contractor's Overhead Expenses 3.5% 0.035 2521.02
Total 81753.18
Add VAT with adjustment factor. 1.08108 7.5% 0.075 6628.63
Grand Total 88381.81
Rate per no 88382
Rate per each 88382
Help