Breakup

26.74.6 For 10 users

Considering 1 No. septic tank

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Earthwork in excavation Earth-work: 1 x 9'-0" x 5'-6" x 4'-9" = 235.13 cft 235.13 cft 4979.17 % 0 cft 4.98 1170.95
2 One layer brick-flat soling Brick-flat soling: 1 x 8'-6" x 5'-0" = 42.5 sft 42.5 sft 36.19 % sft 0.36 15.3
3 Concrete for slab (1:2:4) 6" R. C.C. (1:2:4) on soling: 1 x 8'-6" x 5'-0" x 0'-6" = 21.25 cft 21.25 cft 20355.5 % cft 203.56 4325.65
4 Concrete for slab (1:2:4) 5" thick R.C.C.(1:2:4) lining 2 x 6'-0" x 4' - 2" x 5" = 21.02 cft 2 x 3'-4" x 4' - 2" x 5" = 11.66 cft = 32.68 cft 32.68 cft 20355.5 % cft 203.56 6652.34
5 Concrete for slab (1:2:4) Tie beam (1:2"4) 1 x 9" x 9" x 2'-6" = 1.41 cft 1.41 cft 20355.5 % cft 203.56 287.02
6 Concrete for slab (1:2:4) R.C.C. in roof slab 1 x 8' - 6" x 5' - 0" x 4" = 14.03 cft 14.03 cft 20355.5 % cft 203.56 2855.95
7 Brick work (1:6) in foundation 10" thick Brick-work (1:6): 2 x 8'-6" x 4'-2" x 0'-10" = 58.8387 cft 2 x 3'-4" x 4'-2" x 0'-10" = 23.05 cft 1x 5'-0" x 1'-6" x 10" = 6.23 cft Total = 88.1187 cft 88.1187 cft 17397.25 % cft 173.97 15330.01
8 5" / 125 mm brickwork (1:6) 5" thick brick-work (1:6) 1 x 1'-11" x 2'-6" = 4.80 sft 4.8 sft 8794.75 % sft 87.95 422.16
9 1/2 " thick plaster (1:4) with N.C.F. 12 mm thic plaster with n.c.f.: Floor: 1 x 6' - 0" x 2' - 6" = 15.00 sft Walls: 2 x 5' - 11" x 4' - 0" = 47.36 sft 2 x 2' - 5" x 4' - 0" = 19.36 sft Tie: 1 x 2' - 7" x 2' - 5" = 6.24 sft Outside: 2 x (8'-6" + 5'-0") x 1'-6" = 40.50 sft = 128.46 sft 128.46 sft 28.39 sft 0.28 35.97
10 RCC tees RCC Tees 2 nos 450 each 450 900
11 Grade 300(300Mpa / 300N/mm2 ≈ 43500psi/40 Grade): BDS- 6935-2006 - B300 and Ratio fy to fu =>1.25 re-inforcement & fabrication 260 lbs 65000 per M. ton 29.48 7664.8
12 Water sealed heavy type 18" / 450 mm dia C.I. M.H. cover having locking arrangement 18" dia water sealed heavy type C.I. man-hole cover with locking arrangement in/c making holes. 2 nos 910 each 910 1820
13 Side filling, dressing, inside cleaning etc. LS 800
Sub-Total 42280.15
Contractor's Profit 10% 0.1 4228.02
Contractor's Overhead Expenses 3.5% 0.035 1479.81
Total 47987.98
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3890.91
Grand Total 51878.89
Rate per no 51879
Rate per each 51879
Help