Considering mobilization for 1 set
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Mobilization of equipment for drilling 38 mm dia test and observation well Transportation of materials, equipments, tools and plants, boring rigs to work site for sinking 38 mm test and observation well. | 1 | LS | 6400 | LS | 6400 | 6400 | |
| Sub-Total | 6400 | |||||||
| Contractor's Profit | 10% | 0.1 | 640 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 224 | |||||
| Total | 7264 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 588.97 | ||||
| Grand Total | 7852.97 | |||||||
| Rate per set | 7853 | |||||||
| Rate per set | 7853 | |||||||