Breakup

27.2.1 From 0.0 m to 50 m = 50 m

Considering 0 meter to 50 meter

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Boring by using 100 mm dia cutter (0 m to 50 m) Cost for boring including all equipment, accessories, labours and materials along with insurance coverage of risks 50 meter 160 meter 160 8000
Sub-Total 8000
Contractor's Profit 10% 0.1 800
Contractor's Overhead Expenses 3.5% 0.035 280
Total 9080
Add VAT with adjustment factor. 1.08108 7.5% 0.075 736.22
Grand Total 9816.22
Rate per meter 196.32
Rate per meter 196.32