Considering 0 meter to 50 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Boring by using 100 mm dia cutter (0 m to 50 m) Cost for boring including all equipment, accessories, labours and materials along with insurance coverage of risks | 50 | meter | 160 | meter | 160 | 8000 | |
| Sub-Total | 8000 | |||||||
| Contractor's Profit | 10% | 0.1 | 800 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 280 | |||||
| Total | 9080 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 736.22 | ||||
| Grand Total | 9816.22 | |||||||
| Rate per meter | 196.32 | |||||||
| Rate per meter | 196.32 | |||||||