Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 2.91 mm wall thick 38 mm dia G.I. pipe 38 mm dia G.I. pipe | 1 | meter | 650 | meter | 650 | 650 | |
| 2 | Ordinary labour Labour for fitting, fixing, lowering in/c coverage of risk and solution | 1 | LS | 550 | per day | 151.25 | 151.25 | |
| 3 | Ordinary labour Carriage | 1 | LS | 550 | per day | 27.5 | 27.5 | |
| Sub-Total | 828.75 | |||||||
| Contractor's Profit | 10% | 0.1 | 82.88 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 29.01 | |||||
| Total | 940.64 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 76.27 | ||||
| Grand Total | 1016.91 | |||||||
| Rate per meter | 1017 | |||||||
| Rate per meter | 1017 | |||||||