Considering 1 meter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 38 mm dia water grade PVC Strainer (D-Class or eqv.) including carriage 38 mm dia water grade PVC strainer in/c carriage | 1 | meter | 160 | meter | 160 | 160 | |
| 2 | Ordinary labour Making slot & cleaning | 1 | meter | 550 | per day | 22 | 22 | |
| 3 | Ordinary labour Labour for fitting, fixing, lowering in/c coverage of risk and solution | 1 | LS | 550 | per day | 55 | 55 | |
| Sub-Total | 237 | |||||||
| Contractor's Profit | 10% | 0.1 | 23.7 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 8.29 | |||||
| Total | 268.99 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 21.81 | ||||
| Grand Total | 290.8 | |||||||
| Rate per meter | 291 | |||||||
| Rate per meter | 291 | |||||||