Considering 1 No.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 38 mm dia socket adopter 38 mm dia socket adapter | 1 | no | 80 | each | 80 | 80 | |
| 2 | Ordinary labour Labour for fitting, fixing, lowering in/c coverage of risk and solution | 1 | LS | 550 | per day | 27.5 | 27.5 | |
| Sub-Total | 107.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 10.75 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 3.76 | |||||
| Total | 122.01 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 9.89 | ||||
| Grand Total | 131.9 | |||||||
| Rate per each | 132 | |||||||
| Rate per each | 132 | |||||||