Considering 1 No.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Skilled technician Cost of plate/pillar | 1 | no | 1200 | per day | 1680 | 1680 | |
| 2 | Skilled technician Cost of writing information | 1 | LS | 1200 | per day | 1440 | 1440 | |
| 3 | Skilled technician Cost of fittings and labour for erection or fitting, fixing etc. | 1 | LS | 1200 | per day | 960 | 960 | |
| Sub-Total | 4080 | |||||||
| Contractor's Profit | 10% | 0.1 | 408 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 142.8 | |||||
| Total | 4630.8 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 375.47 | ||||
| Grand Total | 5006.27 | |||||||
| Rate per each | 5006 | |||||||
| Rate per each | 5006 | |||||||