27.3.7 Supplying, fitting & fixing tube-well log describing technical information of the tube-well

Considering 1 No.

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled technician Cost of plate/pillar 1 no 1200 per day 1680 1680
2 Skilled technician Cost of writing information 1 LS 1200 per day 1440 1440
3 Skilled technician Cost of fittings and labour for erection or fitting, fixing etc. 1 LS 1200 per day 960 960
Sub-Total 4080
Contractor's Profit 10% 0.1 408
Contractor's Overhead Expenses 3.5% 0.035 142.8
Total 4630.8
Add VAT with adjustment factor. 1.08108 7.5% 0.075 375.47
Grand Total 5006.27
Rate per each 5006
Rate per each 5006