For 1 No. test tube-well
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Complete development of the tube-well (test boring) up to 200 m depth. Cost for wells up to 200 m depth: sample of water must be taken from 3 aquifier level from 1 test tube-wells | 1 | no | 7200 | LS | 7200 | 7200 | |
| Sub-Total | 7200 | |||||||
| Contractor's Profit | 10% | 0.1 | 720 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 252 | |||||
| Total | 8172 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 662.59 | ||||
| Grand Total | 8834.59 | |||||||
| Rate per each | 8835 | |||||||
| Rate per each | 8835 | |||||||