Breakup

27.5.1 Furnishing design considering 1 No. test bore

Taking consideration of 1 no test bore

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Field Engineer ( minimum BSc in Eng. with 3yrs exp OR Diploma in Eng. with 8yrs exp) Cost for furnishing design of tube well 1 LS 1900 per day 2533.33 2533.33
2 pH/Hydrogen Ion density Testing of water collected from the test bore: pH/Hydrogen ion density 1 test 500 per test 500 500
3 Carbon dioxide (CO2) Carbondioxide (CO2) 1 test 500 per test 500 500
4 Chlorine (Cl) Chlorine (Cl) 1 test 800 per test 800 800
5 Fluorine (Fl) Fluorine (Fl) 1 test 700 per test 700 700
6 Iron (Fe) Iron (Fe) 1 test 2500 per test 2500 2500
7 Manganese (Mn) Manganese (Mn) 1 test 1800 per test 1800 1800
8 Nitrate-Nitrogen (NO3-N) Nitrate-Nitrogen (NO3-N) 1 test 900 per test 900 900
9 Total Alkalinity Total alkalinity 1 test 600 per test 600 600
10 Total hardness Total hardness 1 test 1100 per test 1100 1100
11 Arsenic (As) Arsenic (As) 1 test 1800 per test 1800 1800
12 Turbidity Turbidity 1 test 500 per test 500 500
13 Sieve analysis for sand from different layer Sieve analysis for sand from different layer 3 tests 3800 per test 3800 11400
14 Field Engineer ( minimum BSc in Eng. with 3yrs exp OR Diploma in Eng. with 8yrs exp) Maintaining the bore holes and tools and plants etc. at site untill satisfactory results are obtained from laboratory, filling and sealing the bore holes 1 no 1900 per day 5066.67 5066.67
Sub-Total 30700
Contractor's Profit 10% 0.1 3070
Contractor's Overhead Expenses 3.5% 0.035 1074.5
Total 34844.5
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2825.23
Grand Total 37669.73
Rate per each 37670
Rate per each 37670