Breakup

27.7.1 For Tube-wells up to 100 meter depth

considering 1 set

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Mobilization of drilling rig for shrouded production wells of depth up to 100 m Mobilization of complete set of boring rig etc. for sinking up to 100 meter depth 1 LS 39100 LS 39100 39100
Sub-Total 39100
Contractor's Profit 10% 0.1 3910
Contractor's Overhead Expenses 3.5% 0.035 1368.5
Total 44378.5
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3598.25
Grand Total 47976.75
Rate per set 47977
Rate per set 47977