considering 1 set
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Mobilization of drilling rig for shrouded production wells of depth up to 100 m Mobilization of complete set of boring rig etc. for sinking up to 100 meter depth | 1 | LS | 39100 | LS | 39100 | 39100 | |
| Sub-Total | 39100 | |||||||
| Contractor's Profit | 10% | 0.1 | 3910 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1368.5 | |||||
| Total | 44378.5 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 3598.25 | ||||
| Grand Total | 47976.75 | |||||||
| Rate per set | 47977 | |||||||
| Rate per set | 47977 | |||||||