325 mm dia Considering 0 m to 50 m
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 325 mm dia boring: up to 50 m depth. Cost for boring including all equipment, accessories, labours and materials along with insurance coverage of risks | 50 | meter | 780 | meter | 780 | 39000 | |
| Sub-Total | 39000 | |||||||
| Contractor's Profit | 10% | 0.1 | 3900 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1365 | |||||
| Total | 44265 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 3589.05 | ||||
| Grand Total | 47854.05 | |||||||
| Rate per meter | 957.08 | |||||||
| Rate per meter | 957.08 | |||||||